Project A
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $500,000 |
Duration | 900 days |
Status | 600 days |
EV | $180,000 |
PV | $150,000 |
AC | $178,000 |
BAC | ? |
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Project A
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $500,000 |
Duration | 900 days |
Status | 600 days |
EV | $180,000 |
PV | $150,000 |
AC | $178,000 |
BAC | ? |
Assume the spend rate continues for the rest of the project future
1) ETC =
2) EAC =
3) VAC =
Question 2 options:
Project B
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $220,000 |
Duration | 350 days |
Status | 240 days |
EV | $180,000 |
PV | $180,000 |
AC | $192,000 |
BAC | ? |
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Question 3 options:
Project B
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $220,000 |
Duration | 350 days |
Status | 240 days |
EV | $180,000 |
PV | $180,000 |
AC | $192,000 |
BAC | ? |
Assume that the same spend rate continues for the rest of the project
1) ETC =
2) EAC =
3) VAC =
Question 4 options:
Project C
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $4.600,000 |
Duration | 600 days |
Status | 80 days |
EV | $540,000 |
PV | $580,000 |
AC | $980,000 |
BAC | ? |
Assume that future cost estimates are accurate and do not change.
1) ETC =
2) EAC =
3) VAC =
Question 5 options:
Project C
You are given the following data regarding the Earned Value results of a project. There are no approved change orders for this project. Calculate ETC, EAC and VAC.
Budget | $4.600,000 |
Duration | 600 days |
Status | 80 days |
EV | $540,000 |
PV | $580,000 |
AC | $980,000 |
BAC | ? |
Assume that the same spend rate continues
1) ETC =
2) EAC =
3) VAC =
Question 6 options:
Review the results in Project C and make a recommendation about the project budget.